Renovation Process
01. Preliminary Preparation
Estimate costs & allocate budget
Plan layout and functionality
Select design & construction method
⏱ Duration: Not fixed
📝 Note: Cabinet measurements appointment happens during this stage.
02. Demolition & New Construction
On-site protection
Demolition (based on condition)
Wall modifications (if needed)
⏱ Duration: 7–15 working days
03. Plumbing & Electrical Work
Water & electricity layout modification
Install bathroom/kitchen plumbing, flooring heating, central air conditioning
⏱ Duration: 7–15 working days
✅ Mid-term Inspection
04. Tiling (Masonry Work)
Floor leveling, backfilling
Waterproofing, water pressure testing
Tile installation
Grouting
⏱ Duration: 7–15 working days
05. Carpentry Work
Ceiling installation
TV cabinet platform (if needed)
Decorative structures (if needed)
⏱ Duration: 7–15 working days
📝 Note: Carpentry and tiling often alternate or overlap in actual work depending on the site conditions.
📌 During Steps 4–5:
Cabinet, door, window measurements
Gas line rework
Stone materials ordered
06. Painting (Finishing Work)
Wall putty
Base treatment
Painting/wallpapering
Cabinet surface spraying (if needed)
⏱ Duration: 5–10 working days
07. Installation
Kitchen and bathroom fittings
Flooring, skirting
Window ledges
Doors, door frames, window frames
Custom furniture
Radiant heating (if applicable)
Switches, sockets, lights
⏱ Duration: 5–10 working days
08. Soft Furnishing Stage
Curtains, furniture, decor, etc. enter the space