Renovation Process
01. Preliminary Preparation
-
Estimate costs & allocate budget
-
Plan layout and functionality
-
Select design & construction method
-
⏱ Duration: Not fixed
📝 Note: Cabinet measurements appointment happens during this stage.
02. Demolition & New Construction
-
On-site protection
-
Demolition (based on condition)
-
Wall modifications (if needed)
-
⏱ Duration: 7–15 working days
03. Plumbing & Electrical Work
-
Water & electricity layout modification
-
Install bathroom/kitchen plumbing, flooring heating, central air conditioning
-
⏱ Duration: 7–15 working days
✅ Mid-term Inspection
04. Tiling (Masonry Work)
-
Floor leveling, backfilling
-
Waterproofing, water pressure testing
-
Tile installation
-
Grouting
-
⏱ Duration: 7–15 working days
05. Carpentry Work
-
Ceiling installation
-
TV cabinet platform (if needed)
-
Decorative structures (if needed)
-
⏱ Duration: 7–15 working days
📝 Note: Carpentry and tiling often alternate or overlap in actual work depending on the site conditions.
📌 During Steps 4–5:
-
Cabinet, door, window measurements
-
Gas line rework
-
Stone materials ordered
06. Painting (Finishing Work)
-
Wall putty
-
Base treatment
-
Painting/wallpapering
-
Cabinet surface spraying (if needed)
-
⏱ Duration: 5–10 working days
07. Installation
-
Kitchen and bathroom fittings
-
Flooring, skirting
-
Window ledges
-
Doors, door frames, window frames
-
Custom furniture
-
Radiant heating (if applicable)
-
Switches, sockets, lights
-
⏱ Duration: 5–10 working days
08. Soft Furnishing Stage
-
Curtains, furniture, decor, etc. enter the space